The last stator frame at the Suki Kinari hydropower project in Mansehra has been hoisted successfully and lowered into the unit pit.
The project has four electricity generation units with a combined capacity of 884 megawatts.
The run-of-river facility is one of the early-harvest clean energy projects under China-Pakistan Economic Corridor.
The existing portion of N-15 will submerge in the reservoir of the Suki Kinari hydropower project; therefore, the new road was constructed at a higher elevation.
The new road also has a 411-metre-long tunnel. The project is expected to complete by the end of next year.